Project: MTM – Victoria Park Station Lighting Upgrade Project

Victoria Park Station Transformed with Improved Lighting and Enhanced Visibility

As part of the Better Stations 3.0 program, Metro Trains Melbourne (Metro) engaged Everon Infrastructure to deliver lighting upgrade works at Victoria Park Station.

The Victoria Park Station upgrade improved lux levels and delivered consistent lighting across the entrance ramps and subway areas. Completed within a live station environment, the project included electrical, structural and lighting works to address compliance issues, replace ageing infrastructure and improve the long-term reliability of the station’s lighting systems. These upgrades enhanced visibility, passenger safety and the overall customer experience.

PROJECT SCOPE:

Electrical & Lighting Works 

  • Supply and installation of cable containment and cabling from existing station distribution boards to new lighting.
  • Installation of LED fittings on new and existing poles.
  • Installation of LED lighting within the subway, PSO Pod and Platform 2 canopy.
  • Installation of a new distribution board at Platform 1 and upgrades to existing boards.

Structural & Civil Works 

  • Installation of a new ramp-mounted light pole at the Platform 2 entrance.
  • Supply and installation of supporting structural steelwork for the ramp-mounted pole.
  • Installation of five new in-ground light poles along the Platform 1 and Platform 2 entrance ramps.

Work with asbestos

  • Specialist asbestos contractors completed the required works under controlled conditions, ensuring safety and regulatory compliance.

Client: Metro Trains Melbourne

Location: Abbotsford, Melbourne

Date: August 2025